๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

City of Schertz Curtiss Avenue Sidewalk Addition Project

Curtiss Ave. from Westchester Dr. to FM 1518, Schertz, TX 78154, Schertz, TX, 78154
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021000418
$315K
Project Value
26,460
Square Feet
$12/sqft
Cost/SqFt
3 months
Duration
Registered:Sep 8, 2020
Start:Sep 14, 2020
Target:Nov 30, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Install new sidewalk along the south side of Curtiss Avenue from Westchester Drive to F.M. 1518. Install new ADA compliant sidewalk ramps at all corners to provide accessible path.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 8, 2020
Construction Start
September 14, 2020
Expected Completion
November 30, 2020