๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Playground and Parking Improvements Cross Timbers Park

101 Stagecoach Trail, Willow Park, TX 76087, Willow Park, TX, 76087
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020021703
$500K
Project Value
40,000
Square Feet
$13/sqft
Cost/SqFt
4 months
Duration
Registered:Aug 4, 2020
Start:Oct 1, 2020
Target:Feb 1, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Playground and Parking Lot

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 4, 2020
Construction Start
October 1, 2020
Expected Completion
February 1, 2021

Quick Actions

TDLR ID: TABS2020021703

Property Owner

Design Firm

๐Ÿ›๏ธ
Pacheco Koch
4 projects ยท $616.5M
4060 Bryant Irvin Road, Fort Worth, Texas 76109

Registered Accessibility Specialist

๐Ÿ“‹
FRED DWAIN,CAWYER
RAS #86
8301 LAKEVIEW PKWY # 111-303, ROWLETT, TX 75088