BS 35C (CSJ: 0178-08-017)
From: SH 35 N To: FM 1462, Alvin, TX, 77511
Construction50%
๐Project Metrics
TDLR #TABS2025011626$7.1M
Project Value
1,000
Square Feet
$7116/sqft
Cost/SqFt
8 months
Duration
Registered:Feb 11, 2025
Start:Jul 1, 2025
Target:Mar 12, 2026
Remaining:92 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Pavement repair, 3 inch mill, asphalt concrete pavement overlay, signing, striping and upgrade of intersection traffic signals.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 11, 2025
Review Complete
February 11, 2025
Construction Start
July 1, 2025
Expected Completion
March 12, 2026
Property Owner
๐ค
TxDOT District: Houston
Contact: Jonathan Philip Espiritu, P.E.
6 projects ยท $107.4M
7600 Washington Avenue, Houston, Texas 77007